A job cost variance measures the difference between actual cost and the allowed cost for the same completed scope. It does not explain the cause. Start with one work package, such as ground-floor partitions, rather than a whole-job total that can hide opposing differences.
The early signs that a job is losing money tell you where to look.
Use this sign convention throughout: adverse cost variance = actual cost minus comparable allowed cost. A positive result means adverse cost variance. A negative result means favourable cost variance.
This reverses the earned value management convention. The AACE 86R-14 sample guidance defines cost variance as earned value minus actual cost, or EV minus AC. In that convention, a negative result is adverse. Label your report clearly. AACE describes a recommended practice, not a standard.
Choose a cut-off date. Measure completed output against the agreed specification at that date. Then calculate the allowed cost for that output from the estimate. Do not compare partial actuals with the full-job budget as proof of performance.
Keep the basis consistent. Compare costs excluding VAT if the estimate excludes VAT. Use the same treatment of labour burden and site overheads on both sides. Record these choices beside the package reference so another person can repeat the calculation.
Check the evidence before asking the supervisor to explain a loss. Match time records to work dates. Reconcile material consumption with deliveries, returns and stock left on site. For subcontractors, match incurred cost to measured completed work, not merely the payment date.
An unpaid invoice can represent incurred cost. A purchase order for future work is a commitment, not actual cost. Show commitments separately when estimating the cost to finish. Include incurred but unposted costs through your normal accounting process, then prevent duplication when invoices arrive.
Approved scope needs its own allowance. Use the written approval and its cost build-up, not the extra selling price. If the record is missing, follow the process for recording variations agreed on site. Keep disputed scope visible rather than quietly treating it as approved.
This invented example concerns a completed partition package within an unfinished fit-out. All figures exclude VAT. All package output is complete at Friday's cut-off, including an approved extra section, with no unused material stock or unposted incurred cost.
The original allowance for this completed output was £10,000. The approved addition has a separate cost allowance of £800. Recorded actual cost is £12,000, but £300 belongs to another package.
| Reconciliation step | Amount |
|---|---|
| Recorded actual cost | £12,000 |
| Remove cost coded to the wrong package | −£300 |
| Correct actual cost | £11,700 |
| Original allowed cost | £10,000 |
| Add approved scope allowance | £800 |
| Comparable allowed cost | £10,800 |
| Adverse cost variance | £900 |
The raw £2,000 difference is therefore not a £2,000 performance loss. It contains a £300 coding error and an £800 scope allowance adjustment. The coding correction moves cost elsewhere; it does not reduce total job cost.
Now reconcile the corrected package by cost type. Keep the approved addition separate so its costs do not enter the original materials calculation.
| Cost type | Comparable allowed cost | Correct actual cost | Actual minus allowed |
|---|---|---|---|
| Original-scope labour | £4,000 | £4,200 | £200 |
| Original-scope materials | £4,000 | £4,400 | £400 |
| Original-scope subcontractors | £2,000 | £2,300 | £300 |
| Approved addition, all costs | £800 | £800 | £0 |
| Total | £10,800 | £11,700 | £900 |
Nothing remains unexplained arithmetically. The timing adjustment is zero because the cut-off review found no missing costs, but that does not prove why labour or materials cost more.
Start with the original completed partitions only. Use the material allowance from the estimate and the consumption reconciled to that same output. Exclude the approved addition. Its allowance and actual cost already sit together in a separate row, so neither belongs in this bridge.
Use boards of the same grade and dimensions. Treat delivery charges consistently in both unit prices before you calculate either effect. Do not use total purchases in place of consumption when unused stock remains on site or materials have moved to another package.
In this example, the verified allowance is 250 boards at £16, and actual consumption is 220 boards at £20. Both quantities relate to the same completed original scope. The allowance totals £4,000; actual materials cost totals £4,400.
| Bridge component | Calculation | Effect |
|---|---|---|
| Quantity effect at allowed price | (220 − 250) × £16 | −£480 |
| Price effect on actual quantity | (£20 − £16) × 220 | £880 |
| Net adverse materials cost variance | −£480 + £880 | £400 |
Lower consumption partly offsets a higher unit price, but the net figure hides both changes. Calculate quantity at the allowed price and price on actual quantity. This counts their interaction once; do not add another interaction charge.
These are arithmetic drivers, not proven root causes. Fewer boards might reflect better cutting or an inflated allowance. A higher unit price might reflect late ordering, a changed specification or an estimating error. Check comparable board grades and units before accepting either explanation.
Create one investigation row per driver. Include the decision, evidence, action, owner and forecast effect. Give unresolved rows a due date. Do not replace missing evidence with a confident label such as “poor productivity”.
In this ledger, which continues the invented example, each forecast instruction applies only to work that remains, not to costs already incurred.
| Driver or check | Decision and evidence | Action | Owner | Forecast effect |
|---|---|---|---|---|
| Labour: £200 adverse | Extra hours proven; cause open pending daily records | Compare access restrictions with work dates | Site manager | Re-estimate remaining hours after review |
| Materials quantity: £480 favourable | Consumption reconciled; improved cutting not proven | Check cutting records against allowance | Estimator | Do not repeat the saving yet |
| Materials price: £880 adverse | Order history proves expired quote used in estimate | Obtain current prices for remaining boards | Buyer | Replace stale unit prices |
| Subcontractors: £300 adverse | Agreed valuation proves extra attendance after access failure | Confirm next access date before booking | Contracts manager | Price any further attendance once |
| Timing: £0 | Cut-off review reconciles incurred costs | Retain reconciliation | Accounts lead | No timing adjustment |
| Coding: £300 removed | Source record identifies another package | Correct both package records | Accounts lead | No total-job saving |
| Approved scope: £800 allowance and actual | Approval and separate cost records agree | Retain separate scope reference | Quantity surveyor | No remaining work for this addition |
A price difference proves what changed. The expired quote identifies an estimating error in this example, but does not explain the supplier's higher price. The quantity difference remains unexplained despite a complete reconciliation. Keep that distinction visible until the estimator tests the allowance.
Test the explanation. If a supervisor says blocked access caused extra hours, ask for dated records. These must connect the restriction to the affected crew and completed work. A general complaint cannot separate waiting time from rework, an incorrect allowance or time booked against the wrong package that week.
Leave the cause open when the records cannot distinguish between possible explanations. Name the person who must obtain the evidence before the next review. Do not invent certainty.
The GAO Cost Estimating and Assessment Guide includes documenting assumptions and updating estimates with actual costs. It addresses government programme estimates; it is not a mandate for builders. Its useful principle here is traceability: show why each remaining allowance changes.
AACE also connects root cause analysis, corrective action and the estimate to complete. Apply that sequence to this ledger. Add corrected actual cost to a fresh estimate of remaining work. Include commitments within that remaining estimate without counting them again as actual cost.
Do not spread the £900 across the unfinished job by percentage. The expired price may affect future orders; completed extra attendance may not recur. Record an expected recovery only when the action and its cost effect have support.
Korrel can compare recorded time and costs with estimates. Keep this materials investigation in a separate ledger; do not assume automatic purchasing or quantity-price analysis. The cost-tracking guides cover the wider review process.
To track recorded time and costs against your estimates, create a Korrel account.
RELATED READING:
A role variance bridge shows whether an architectural project cost more because of extra hours, a different staff mix, or changed cost rates.
Group completed consultancy work by type. Compare estimated and actual effort, find repeated bias, and correct one estimate component at a time.
Set timesheet timing from the decision the data must support. Use this freshness policy to keep staffing, margin, billing, and estimates current.
Korrel turns briefs into structured proposals, then tracks what each job actually costs.
START FREE TRIAL