Implementation restart costs cover the supplier's additional work and purchases needed to resume delivery. Estimate these alongside the original work still required. Keep costs already incurred separate.
Do not simply reuse the unspent allowance. Check what you can retain and what remains unfinished. Then check what the pause changed. Separate your delivery cost from the price you might ask the client to approve.
A buyer's delayed savings belong in its business case. They are not your implementation labour or supplier expense. Do not add those lost benefits to your delivery-cost total.
Use the ledger below for an implementation with completed configuration and unfinished migration. The team must also rebuild its project knowledge. The amounts and hours are invented, as are the circumstances. They illustrate a costing method, not an industry benchmark or a recommended charge.
Start with evidence, not a completion percentage. Collect the scope version, accepted outputs, test results, recorded actual costs and unresolved decisions from the suspension date.
Then inspect the current environment. Check access, software versions, integration behaviour, test data and the people available to finish delivery. Give each check an owner and a recorded result.
Kurt Stoever and Holly Trella wrote the PMI conference paper on managing IT project restarts. They recommend checking assumptions again and reviewing estimates. Their review also covers staffing and supplier commitments. The paper dates from September 2000. Use it as historical process guidance, not evidence of current project outcomes or demand.
Classify each output as usable, incomplete, requiring repair, or no longer required. Record why. Keep an accepted configuration as completed work if it still meets the requirement. Cost any new compatibility check separately.
Do not erase old actual costs when an output becomes unusable. Those costs remain part of project history. Estimate replacement or repair effort as future work, with a reason that distinguishes it from the original task.
This is also the point to refresh your fixed-fee implementation margin forecast. The cost still needed must reflect today's delivery plan, not the old timetable with new dates.
The invented project had an original delivery-cost allowance of £40,000. At suspension, usable completed work had cost £16,000 against an allowance of £16,000. The original remaining allowance was therefore £24,000.
Assume no other work costs had been incurred. No original contingency remains to allocate, and all figures use the same cost basis. Labour uses internal cost rates, not client billing rates. Amounts exclude VAT and selling margin.
Set the estimate date one week before the proposed restart. The supplier has already incurred £900 of hosting costs during the pause. Another £300 will arise before the proposed restart date.
| Cost category | Evidence or calculation | Treatment |
|---|---|---|
| Usable completed work | Accepted configuration, £16,000 actual cost | Historical cost only |
| Remaining original work | Migration, testing and training, £24,000 old allowance | Re-estimate for delivery |
| Additional restart effort | Checks, handover and plan revision, £3,440 | Future restart cost |
| Continuing pause costs | £900 incurred; £300 still expected | Split past and future |
| Updated supplier prices | Migration support rises from £4,000 to £4,600 | Add only the £600 difference |
The £24,000 remaining allowance includes £4,000 for migration support. All other original remaining costs stay unchanged in this example. Replacing that supplier allowance adds £600, not the full £4,600 again.
Grant Thornton India's guidance on halting and resuming IT projects identifies items to review. These include knowledge transfer, idle software costs and price increases. It is buyer-side pandemic guidance dated 24 April 2020, not a current supplier pricing standard. Use those categories to investigate your own costs. Do not assume every category applies.
For this supplier, the pause expense is project-specific hosting. Exclude a licence paid directly by the buyer. Also exclude a general company subscription unless your normal costing method allocates it here without duplication.
Make each restart task testable. Name its output and role. Record its hours and cost rate. The invented team estimates the following work outside its original remaining allowance.
| Additional restart task | Hours and internal cost rate | Cost |
|---|---|---|
| Check environment and integration versions | 12 architect hours at £80 | £960 |
| Transfer knowledge to replacement consultant | 20 consultant hours at £60 | £1,200 |
| Update plan and confirm dependencies | 8 project manager hours at £70 | £560 |
| Repeat compatibility tests after platform changes | 12 tester hours at £60 | £720 |
| Total additional restart effort | 52 hours | £3,440 |
The original allowance still covers functional acceptance testing. The extra test task checks only compatibility affected by changes during the pause. If the tests overlap, remove the repeated hours from one category.
The same rule applies to handover. Do not add a separate handover allowance if the remaining delivery estimate already includes those hours. Give every future task one cost location.
Request a fresh written supplier quote. Compare the same scope, quantities, support period and currency before treating a difference as a price change. Record the quote's validity date too.
If access remains unavailable, label the estimate provisional. Define the limits of an inspection task before committing to the full restart. An unsupported percentage increase does not explain what work you expect to do.
Keep a separate list of unresolved assumptions. For example, name the platform version used for the compatibility estimate and the person who will confirm it. Give that confirmation a deadline. If it fails, revise the affected task rather than adding an unexplained amount to every cost category.
Do not assume the replacement consultant can start on the old date. Confirm availability before you issue the plan. If the restart moves, recalculate the future hosting period and check the supplier quote again. Preserve the previous estimate version so the next review can explain each difference.
The revised delivery cost from the restart date is £28,040. This comprises the £24,000 original remaining allowance, plus the £600 supplier price increase, plus £3,440 restart effort.
The remaining cost from the estimate date is £28,340. That includes the £300 future pause cost before restart. It does not include the £900 already incurred during the pause.
The full project cost forecast is £45,240: £16,000 completed work, £900 incurred pause cost, and £28,340 future cost. This is a cost forecast, not a proposed client fee.
Check the difference against the original £40,000 allowance. The increase is £5,240: £1,200 total pause costs, £600 supplier price increase and £3,440 restart effort. The two calculations agree.
Do not add the original £40,000 to the remaining-cost estimate. It already contains both completed and unfinished work. Similarly, do not add £16,000 of completed work to the remaining-cost estimate.
Classify costs by service period, not invoice date, in this ledger. Check when the service was supplied. Reconcile commitments and actual costs so an unpaid supplier bill does not appear in both categories.
Your cost estimate shows what delivery will cost. It does not establish what the client must pay. Give the proposed price its own field. Record internal approval separately from the client decision, each in its own field.
Prepare a short decision note with the retained outputs, additional tasks, revised dates and assumptions. State which costs your business proposes to absorb. Show any proposed extra fee separately from internal cost.
If the client questions a new task, compare it with the agreed scope. Use the same evidence-led approach as telling a client work is out of scope. A pause does not, by itself, prove that every restart task is extra scope.
Keep the resulting decision with your change-control records. Record who approved the delivery plan and who accepted any proposed price. Do not treat an internal approval as client acceptance.
Korrel supports on-hold project status and time and expense records. It also supports change requests with cost and revenue impact previews. It does not provide client approval capture. Build and review the restart ledger yourself.
Create a Korrel account to track delivery time and expenses against the work you estimated.
RELATED READING:
The money is lost in the ninety seconds between a client asking for a change and a trade starting it. Here is the pause, price and confirm sequence that closes it.
A fixed price SOW gives you one number and no invoice line to check yourself against. Convert it into a cost ledger, then reconcile actuals every week.
A fixed-price job goes wrong in week three, not at the final account. These are the leading indicators that show it, and the weekly checks that surface them.