Skip to content

THE MARGIN PLAYBOOK

You quote project work. Some of it earns less than you priced.

This is how to find out what they actually earned.

Four minutes to read. Four to five days to run properly, and the work is rather the point.

START HERE

Check one finished job

Compare the gross margin you planned with the gross margin the job delivered. Use the same delivery-cost basis for both figures. We do not apply an industry benchmark.

The calculation runs in your browser. The figures are not submitted or tracked.

Original quote plus approved changes.

Expected labour, materials, and subcontract costs, including approved changes.

Use the same cost categories as the estimate. A best current figure is fine.

YOUR RESULT

Use a completed job, not an industry average.

If you cannot find the actual delivery cost yet, that is the first useful finding. Move 1 shows where to pull it from.

See Move 1

THE PLAYBOOK

Five moves, and none of them need us

Every move below runs in a spreadsheet. The worked example is an invented commercial fit-out. Its figures come from one tested model, so they stay consistent throughout.

Run properly across ten jobs, this is four to five days of work.

34.3% gross margin, Priced to make

Move 1 of 5

Priced to make

34.3%

  1. 01

    Pull your last ten finished jobs

    Do this

    Four numbers each. What you quoted, what it cost you, the margin you planned, the margin you got. Ten rows in a spreadsheet.

    Worked example & time by hand

    On the worked example

    Clerkenwell was quoted at £100,270, priced to make 34.3%. It delivered 28%.

    By hand

    About a day. Most of that is finding the numbers, which is itself the finding.

  2. 02

    Split every gap by cause

    Do this

    Not that you went over. Where. Labour, materials, subcontract, and anything a change added. One line each.

    Worked example & time by hand

    On the worked example

    812 hours against 748 forecast. That reads as a 8.6% labour overrun, and it is the wrong answer.

    By hand

    Two or three hours a job.

  3. 03

    Count what each change bought, hours as well as money

    Do this

    A change adds revenue. It also adds work. Put both on the job. Almost everyone logs the money and stops there, and the forecast quietly stays where it was.

    Worked example & time by hand

    On the worked example

    The Clerkenwell change was raised, priced, approved and billed: £8,400 onto the contract. The 85 hours it bought never reached the forecast. Measured against 833, labour came in 2.5% under.

    By hand

    An hour, and an uncomfortable one.

  4. 04

    Work out a correction per category, with a sign on it

    Do this

    One percentage per cost category, from your own ten jobs. Positive where you underprice. Negative where you overprice. This is the number a gut feel cannot give you.

    Worked example & time by hand

    On the worked example

    Materials and site costs +23.9%. Labour -2.2%. Subcontract +1.5%. A flat +8.3% across everything would have been wrong three times over.

    By hand

    An hour, once the first three moves are done.

  5. 05

    Price the next job with it, and write down what you assumed

    Do this

    Apply the correction where it belongs. Then record what you priced against, so the next post-mortem has something to check rather than a memory to argue with.

    Worked example & time by hand

    On the worked example

    The next job of this shape prices materials up and labour slightly down. Neither is a guess any more.

    By hand

    Ongoing. It is the move everyone skips, and skipping it is why move one takes a day.

Want the worksheet?

The five moves with columns for final revenue, expected and actual costs by category, approved changes, and the correction each category needs. The totals work themselves out at the bottom.

We will email the spreadsheet immediately. No mailing list or follow-up.

AFTERWARDS

This is the loop we close for you

Everything above is doable by hand. Once. Doing it after every finished job is the part nobody sustains, and that is the whole of what Korrel is for. The correction updates itself as work completes, and the next estimate starts from it instead of from optimism.

See the product walkthrough

The full walkthrough, from brief to sign-off to what the finished job teaches.