# How to record internal rework time on an agency project
Source: https://korrel.ai/blog/record-internal-rework-time-agency-project
Published: 2026-11-25
Updated: 2026-11-24
Topic: internal rework time
Tags: time-tracking, cost-tracking
---
## Keep internal rework time on the project

Internal rework time is time your agency spends correcting its own work to meet an already agreed requirement. Record it against the client project. Keep the hours and their delivery cost, even when you decide not to charge the client anything extra.

The cost happened. A billing decision does not remove it.

Use separate records for what happened and what you will charge. The first explains the work done. The second follows the commercial agreement. Your project lead must check that agreement before anyone sends an extra charge. Neither record should overwrite the other.

This guide uses a manual classification method, not an accounting standard or a rule about what clients must pay. Its worked example keeps the same hours and cost before and after classification. Only the explanation changes.

For the wider recording process, use the [time tracking guides](/blog/topics/time-tracking). Here, the specific task is to make corrections visible without mislabelling every review as a failure.

## Is it a correction, a review or added scope?

Start with the approved brief and the version the team used. What requirement does the work serve?

An included review is part of the agreed delivery process. A client choosing between planned design options does not, by itself, prove that your team made an error. Keep that review within normal delivery unless the evidence shows otherwise.

A correction restores an agreed requirement. For example, your designer exports artwork with the wrong dimensions despite having the correct specification. Record the correction as internal rework, with a reference to that specification.

Added scope changes what you agreed to deliver. A new campaign format is not a correction just because the client requests it during a review. Goodwill describes your decision to absorb a cost, not the technical reason for the work.

The [Association for Project Management defines change control](https://www.apm.org.uk/resources/what-is-project-management/what-is-change-control/) around requests to change an approved baseline. A baseline is the agreed starting plan. Its process includes evaluation and a decision to approve, reject or defer the change.

Apply that distinction to the brief. Do not treat the arrival of feedback as automatic permission to charge. Equally, do not call a new request an internal error just because you choose to do it without an extra fee.

If the brief is unclear, leave the cause unresolved. Assign someone to check the version the team received against the requirement the client now describes. Guessing is not classification.

## Record enough detail to explain the hours

Ask each person to record the work when it happens. They need not settle a commercial dispute before recording their time.

Keep these details together:

- The date, person, role and actual duration.
- The client project and affected deliverable.
- A plain description of the work completed.
- The requirement, feedback or request that prompted it.
- The provisional category and any unresolved question.
- The billing decision, its owner and supporting approval.

Use a description such as: “Corrected banner dimensions to match approved specification, version 3.” It identifies both the work and the evidence. “Design changes” does neither.

Split a mixed entry when you have evidence to support the split. If someone recorded review and correction together, check their notes before splitting the hours. Do not invent precise durations afterwards.

Keep the original total. Changing a label must not change the time worked or the rate used to cost it.

Agree these rules before the next job starts. An [internal proposal approval checklist for agencies](/blog/internal-proposal-approval-checklist-agencies) helps you check included reviews and commercial authority before a quote leaves the business.

## A reconciled ledger with unequal cost rates

This is an invented example, not industry data. An agency has recorded one week's work on a campaign project. Its proposal includes one client review, but not a new social format.

The designer's internal cost rate is £40 an hour. The creative director's internal cost rate is £70 an hour. These are delivery cost rates, not client sell rates. This example includes no expenses or separately allocated overheads.

Before classification, the timesheet contains only role totals:

| Role | Recorded hours | Cost rate | Recorded cost |
| --- | ---: | ---: | ---: |
| Designer | 18 | £40 | £720 |
| Creative director | 6 | £70 | £420 |
| Total | 24 | Unequal rates | £1,140 |

The project lead checks the evidence against each time description. They then assign a category to the work each person recorded during the week. The same entries now have an explanation:

| Work category | Designer hours | Director hours | Delivery cost | Extra client charge decision |
| --- | ---: | ---: | ---: | --- |
| Original production | 10 | 2 | £540 | Covered by agreed fee |
| Included client review | 3 | 1 | £190 | Covered by agreed fee |
| Internal error correction | 3 | 2 | £260 | No extra charge |
| Goodwill addition | 1 | 0.5 | £75 | Fee waived by project lead |
| Approved added scope | 1 | 0.5 | £75 | Separate agreed fee |
| Total | 18 | 6 | £1,140 | Not a fee calculation |

The correction cost is 3 × £40 plus 2 × £70: £260. The included review costs £190, but it is not part of that correction total. The goodwill addition is extra work the agency chose to absorb, rather than work needed to fix its error.

Reconcile both dimensions. The categories still contain 24 hours, and their costs still total £1,140. Designer hours remain 18; director hours remain 6. Moving the correction to a non-billable category has not saved £260.

Do not multiply all hours by one blended rate. That would hide the different role costs unless the blended rate exactly represented this staff mix. Keep the rates used for the original entries when you change their categories.

## Keep billing decisions separate from cost recording

In the example, the agreed project fee covers production and the included review. The agency absorbs its correction cost. It also approves a goodwill addition without changing the fee.

The approved added scope has a separate fee agreement. Its £75 delivery cost does not determine the price, and the table does not claim a right to charge it. Check the agreement before billing.

Record who approved the goodwill decision. Keep its reason beside the entry. A later reviewer can then tell whether you chose to waive the charge or have not yet decided.

The [UK Government's Teal Book guidance on change control](https://projectdelivery.gov.uk/teal-book/home/part-e-planning-and-control/chapter-22-change-control/) distinguishes a request from an approved change. It also assigns an owner to each change. This is government project guidance, not an agency billing rule; use the distinction to keep requests separate from decisions.

If a client disputes a charge, keep the delivery cost while the commercial owner resolves the dispute. If you later waive the charge, change the billing record. Do not delete the recorded hours.

For a separate commercial measure, the guide to [agency project recovery rate](/blog/calculate-agency-project-recovery-rate) compares the final fee with time valued at sell rates. Do not confuse that sell-rate comparison with this cost ledger.

## Use the causes to change the next decision

Review the correction entries with the people who did the work. Start with the evidence, not a judgement about an individual.

In this example, the director's correction time costs more per hour than the designer's time. Ask why that role needed to repeat the work. A missing specification check suggests a different action from an unclear handover.

Name one action and its owner. You could check export dimensions before sending artwork, then examine the next comparable job for the same error. Do not infer a lasting pattern from this invented week.

Keep included reviews visible too. They are planned delivery effort, not waste. If they repeatedly exceed their allowance, investigate the allowance and review process without relabelling them as corrections.

## Apply the method without inventing product features

Korrel supports project time entries linked to line items and roles, with billable or non-billable status. It uses the relevant rates to calculate delivery cost. You can compare planned and actual hours and cost.

The cause categories in this guide are a manual method. They are not automatic Korrel rework categories or a dedicated rework report. Use clear entry descriptions and a separate review ledger for the classification.