# Proposal to delivery budget: reconcile the agreed work
Source: https://korrel.ai/blog/reconcile-proposal-opening-delivery-budget
Published: 2026-11-26
Updated: 2026-11-26
Topic: proposal to delivery budget
Tags: proposals, cost-tracking
---
## What does a proposal to delivery budget check establish?

A proposal to delivery budget check connects the agreed client work to the internal hours and costs needed to complete it. It explains each difference from the last internal estimate. The result is an opening baseline: the approved starting plan against which you will compare actual costs.

Do this after final negotiations, before project conversion. Compare the external signed proposal manually with your internal records. Check the work, not just the total fee. A discount can reduce income without removing a single task.

This is a cost reconciliation method, not legal interpretation. It does not decide which document takes precedence or establish contractual entitlement. Refer unclear commitments to the person responsible for the client agreement.

## Fix the starting records before changing the estimate

Keep a dated copy of the last internal estimate. Identify the external agreed document by its title, date and version. Record any confirmed changes that the internal estimate does not yet contain. Do not replace the starting figures while you investigate them.

This check follows the [internal proposal approval checklist](/blog/internal-proposal-approval-checklist-agencies), rather than replacing it. A release review checks what you intend to offer. This reconciliation checks what changed before the client agreed to proceed.

Use stable references for each deliverable. For each reference, retain its description, included work, hours, internal cost rate and allocated client fee. State the currency and tax basis. Mark allowances and exclusions clearly, so a reviewer can see what the cost total contains.

The [APM explanation of cost planning and control](https://www.apm.org.uk/resources/what-is-project-management/what-is-project-cost-planning-and-control/) links an agreed budget to actual and forecast costs. It also describes a cost breakdown structure that sets the level at which costs are collected. For this method, keep the same deliverable references when you begin recording actual costs.

## Classify each difference before you total it

Use four movement types. Keep separate columns for the change in hours, internal cost and client fee. A zero is useful information. It shows that you checked the effect rather than left the column blank.

- **Fee-only concession:** The client pays less for unchanged work. Reduce the fee, not the hours or cost.
- **Removed work:** An agreed output or activity leaves the scope. Remove its documented hours and costs, with the agreed fee reduction.
- **Added promise:** More work enters the scope. Estimate its effort and cost even when the fee does not increase.
- **Internal cost correction:** The internal estimate was incomplete or wrong. Correct the cost without inventing a new client promise.

Split a negotiation decision into separate rows when it has more than one effect. A workshop cancellation and a fee-only concession are not the same movement. Combining them hides how much work actually disappeared.

For each row, record the deliverable reference and source location. Explain the reason for the change. Name its owner and record its review status.

Keep the overall concession separate unless someone has explicitly allocated it. An allocation without evidence can misrepresent the fee for each deliverable.

The [government Cost Estimating Guidance](https://www.gov.uk/government/publications/cost-estimating-guidance/cost-estimating-guidance) calls for traceable assumptions, evidence and cost breakdowns. Its context is major infrastructure, not consultancy proposals. The worked bridge below is our adaptation of those principles, not its prescribed template.

## Worked example: from £20,000 to the opening figures

This consultancy example is invented. All amounts are in pounds, excluding tax. The internal labour cost rate is £60 per hour throughout. It is not a client charge rate or a market benchmark.

The stated cost basis contains only the listed labour and the fixed-cost correction below. It does not include a separate allowance for overhead, tax or other business costs. Real projects need their own complete cost basis.

| Reference and starting work | Hours | Internal cost | Allocated fee |
| --- | ---: | ---: | ---: |
| D1: analysis | 80 | £4,800 | £8,000 |
| D2: workshops | 60 | £3,600 | £6,000 |
| D3: report | 60 | £3,600 | £6,000 |
| Starting total | 200 | £12,000 | £20,000 |

Negotiations produce four changes. There is a £2,000 fee-only concession across the engagement. The client removes 30 workshop hours and £3,000 of fee. An extra report review adds 10 hours without an extra fee. The estimator also corrects an omitted £400 fixed cost.

The fixed cost adds no hours. It is an internal correction, not another client request. Keep it visible rather than spreading it across the labour rate.

| Movement | Hours change | Cost change | Fee change |
| --- | ---: | ---: | ---: |
| Fee-only concession: whole engagement | 0 | £0 | −£2,000 |
| Removed work: D2 workshops | −30 | −£1,800 | −£3,000 |
| Added promise: D3 report review | +10 | +£600 | £0 |
| Internal correction: fixed cost | 0 | +£400 | £0 |
| Net movement | −20 | −£800 | −£5,000 |
| Opening total | 180 | £11,200 | £15,000 |

Check each column independently. Hours are 200 − 30 + 10 = 180. Cost is £12,000 − £1,800 + £600 + £400 = £11,200. Fee is £20,000 − £2,000 − £3,000 = £15,000.

Now rebuild the remaining work. D1 still needs 80 hours and £4,800. D2 needs 30 hours and £1,800. D3 needs 70 hours and £4,200. Labour therefore totals £10,800; the separate £400 correction brings cost to £11,200.

Before the overall concession, the remaining allocated fees are £8,000, £3,000 and £6,000. They total £17,000. The separate £2,000 concession reduces that total to £15,000. No deliverable-level allocation of that concession is assumed.

On this stated cost basis, contribution is £15,000 − £11,200 = £3,800. Contribution divided by fee is £3,800 ÷ £15,000 × 100 = 25.33%, rounded. This is not accounting net profit. It is not a recommended margin.

The fee has fallen much more than the cost. Cutting the hours in line with the fee would erase effort that the team still needs to supply.

## Resolve differences without hiding them in the baseline

Ask a second reviewer to trace every movement back to its source. Confirm that removed workshop work really left the agreed scope. Check that the extra report review appears in the internal description. Confirm the basis of the fixed cost.

Where the records disagree, open a specific question. For example: does the final report include the additional review described in the closing email? Assign the question to the commercial lead. Ask the project lead to assess the effort once the promised output is clear.

Give each unresolved difference an owner, a due date and the decision needed. Do not enter zero merely because nobody has checked the cost. An unknown cost is not a free activity.

Do not convert the proposal if a difference prevents you from identifying the agreed work or its starting allowance. If management accepts a remaining uncertainty, state the assumption. Explain how the budget accounts for its cost. Do not change the original estimate to make the difference disappear.

## Check the conversion preview against the reconciled record

The final proposal to delivery budget check compares line items and totals, not just the headline fee. Match the deliverable references, hours, cost components and included work. Confirm that excluded work has not returned to the project plan.

Korrel supports conversion previews and carries scope, estimate components and payment milestones into projects. Compare that preview manually with the external agreed document and your reconciliation. This is not automatic document comparison. Korrel does not provide native e-signature, client quote sending or CRM integration.

Check milestone allocations separately. In this invented example, two equal allocations of the final £15,000 fee would be £7,500 each. That arithmetic does not establish payment timing or legal terms. The guide to [architect fee payment milestones](/blog/architect-fee-payment-milestones) explains allocation as a separate task.

Keep the approved reconciliation beside the opening record. Use the [proposals topic hub](/blog/topics/proposals) when you need to improve the earlier scope and estimate process.